A project manager discovers additional work that was not included in the project schedule. What should they
Question:
A project manager discovers additional work that was not included in the project schedule. What should they do?
a) Add the work to the project schedule immediately
b) Submit a change request for approval through the Perform Integrated Change Control process
c) Reject the additional work to avoid schedule changes
d) Update the project charter