A project manager discovers additional work that was not included in the project schedule. What should they

Question:

A project manager discovers additional work that was not included in the project schedule. What should they do?

a) Add the work to the project schedule immediately

b) Submit a change request for approval through the Perform Integrated Change Control process

c) Reject the additional work to avoid schedule changes

d) Update the project charter