A project manager is preparing the final project report. What should be included to address cost management?
Question:
A project manager is preparing the final project report. What should be included to address cost management?
a) Detailed project schedule
b) Summary of budget changes and how they were managed
c) List of project stakeholders
d) Project risk assessment