A project manager needs to adjust the communications management plan due to a new regulatory requirement. What

Question:

A project manager needs to adjust the communications management plan due to a new regulatory requirement. What process should they follow?

a) Plan Communications Management

b) Monitor Communications

c) Manage Communications

d) Perform Integrated Change Control