A project manager needs to adjust the procurement management plan due to a change in project scope.

Question:

A project manager needs to adjust the procurement management plan due to a change in project scope. What process should they follow?

a) Plan Procurement Management

b) Control Procurements

c) Conduct Procurements

d) Perform Integrated Change Control