A project manager needs to adjust the procurement management plan due to a change in project scope.
Question:
A project manager needs to adjust the procurement management plan due to a change in project scope. What process should they follow?
a) Plan Procurement Management
b) Control Procurements
c) Conduct Procurements
d) Perform Integrated Change Control
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
PMP Exam Prep 2025 1000 Practice Questions And Answers With Explanation For The PMP Exam
ISBN: 9798227759948
1st Edition
Authors: Claire Georgette Wiman
Question Posted: