A stakeholder identifies a new requirement late in the project. What should the project manager do? a)

Question:

A stakeholder identifies a new requirement late in the project.

What should the project manager do?

a) Implement the requirement immediately to keep the stakeholder happy

b) Evaluate the impact of the new requirement and process it through the change control system

c) Reject the new requirement to avoid scope creep

d) Update the project scope statement without approval