A stakeholder identifies a potential delay in a critical activity. What should the project manager do? a)
Question:
A stakeholder identifies a potential delay in a critical activity.
What should the project manager do?
a) Ignore the delay and continue with the project
b) Evaluate the impact of the delay and take corrective actions if necessary
c) Update the project schedule without approval
d) Request additional resources