A team member identifies a potential improvement for project communication. What should the project manager do? a)

Question:

A team member identifies a potential improvement for project communication. What should the project manager do? a)

Implement the communication improvement immediately

b) Evaluate the improvement and process it through the change control system if it is beneficial

c) Reject the improvement to avoid changes

d) Update the project schedule

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: