A team member identifies a potential improvement for stakeholder engagement processes. What should the project manager do?

Question:

A team member identifies a potential improvement for stakeholder engagement processes. What should the project manager do? a)

Implement the improvement immediately

b) Evaluate the improvement and process it through the change control system if it is beneficial

c) Reject the improvement to avoid changes

d) Update the project schedule