A team member identifies a potential improvement to a deliverable. What should the project manager do? a)

Question:

A team member identifies a potential improvement to a deliverable. What should the project manager do?

a) Implement the improvement immediately

b) Evaluate the improvement and process it through the change control system if it is beneficial

c) Reject the improvement to avoid scope creep

d) Update the project scope statement

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: