A team member identifies a potential improvement to an activity that could reduce its duration. What should

Question:

A team member identifies a potential improvement to an activity that could reduce its duration. What should the project manager do?

a) Implement the improvement immediately

b) Evaluate the improvement and process it through the change control system if it is beneficial

c) Reject the improvement to avoid schedule changes

d) Update the project schedule