Consider a project with the accompanying Gantt chart. Stella is your only electrical engineer and she is
Question:
Consider a project with the accompanying Gantt chart. Stella is your only electrical engineer and she is responsible for activities 3 and 4, which overlap. Level the project so that Stella is only working a maximum of 8 hours each day. What would the new Gantt chart look like? What would be the new project completion date? Consider a project with the following Gantt chart to answer exercises 2 and 3.