Consider the following information for a project: Planned Value (PV): 50,000 euro Earned Value (EV): 40,000 euro
Question:
Consider the following information for a project:
◾Planned Value (PV): 50,000 euro
◾Earned Value (EV): 40,000 euro Based on the given information, calculate the Schedule Variance (SV) for the project and interpret the result.
A. 10,000 euro; the project is ahead of schedule B. −10,000 euro; the project is behind schedule C. 50,000 euro; the project is ahead of schedule D. −50,000 euro; the project is behind schedule
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Mastering The NEW PMI Certified Associate In Project Management (CAPM)® Exam (2023 Version)
ISBN: 9781032611785
1st Edition
Authors: Klaus Nielsen, Giampaolo Marucci, Jean-Luc Favrot
Question Posted: