Consider the following project activities with their durations: Activity A: 5 days; Activity B: 7 days; Activity
Question:
Consider the following project activities with their durations:
◾Activity A: 5 days; Activity B: 7 days; Activity C: 4 days; Activity D: 6 days; Activity E: 8 days and the following dependencies:
◾A -> B; A -> C; B -> D; C -> D; D -> E What is the Float of Activity C in the above schedule network?
A. Float: 0 days B. Float: 1 days C. Float: 2 days D. Float: 3 days