Consider the following project activities with their durations: Activity A: 5 days; Activity B: 7 days; Activity

Question:


Consider the following project activities with their durations:

◾Activity A: 5 days; Activity B: 7 days; Activity C: 4 days; Activity D: 6 days; Activity E: 8 days and the following dependencies:

◾A -> B; A -> C; B -> D; C -> D; D -> E What is the Float of Activity C in the above schedule network?

A. Float: 0 days B. Float: 1 days C. Float: 2 days D. Float: 3 days