During a project, a key stakeholder requests a significant change. What should the project manager do first?

Question:

During a project, a key stakeholder requests a significant change.

What should the project manager do first?

a) Implement the change

b) Assess the impact of the change

c) Reject the change request

d) Escalate the request to the project sponsor