During a project review, a stakeholder requests additional communication updates for a specific activity. What should the

Question:

During a project review, a stakeholder requests additional communication updates for a specific activity. What should the project manager do?

a) Implement the additional updates immediately

b) Evaluate the impact of the additional updates and process the request through the change control system

c) Reject the additional updates to avoid changes

d) Update the project schedule