During a project review, a stakeholder requests additional communication updates for a specific activity. What should the
Question:
During a project review, a stakeholder requests additional communication updates for a specific activity. What should the project manager do?
a) Implement the additional updates immediately
b) Evaluate the impact of the additional updates and process the request through the change control system
c) Reject the additional updates to avoid changes
d) Update the project schedule
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
PMP Exam Prep 2025 1000 Practice Questions And Answers With Explanation For The PMP Exam
ISBN: 9798227759948
1st Edition
Authors: Claire Georgette Wiman
Question Posted: