During a project review, a stakeholder requests additional funding for a specific activity. What should the project
Question:
During a project review, a stakeholder requests additional funding for a specific activity. What should the project manager do? a)
Implement the additional funding immediately
b) Evaluate the impact of the additional funding and process it through the change control system
c) Reject the additional funding to avoid budget changes
d) Update the project budget