During a project review, a stakeholder requests an additional requirement. What should the project manager do first?

Question:

During a project review, a stakeholder requests an additional requirement. What should the project manager do first? a)

Implement the requirement immediately

b) Reject the requirement

c) Evaluate the impact of the requirement on the project scope, schedule, and budget

d) Update the project charter