During a project review, it is found that a critical resource is not available as planned. What

Question:

During a project review, it is found that a critical resource is not available as planned. What should the project manager do first? a)

Update the project charter

b) Implement resource leveling techniques

c) Evaluate the impact of the resource unavailability on the project

d) Request additional resources

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer: