During a project review, it is found that a task is taking longer than expected. What should

Question:

During a project review, it is found that a task is taking longer than expected. What should the project manager do first? a)

Update the project charter

b) Implement schedule compression techniques

c) Evaluate the impact of the delay on the project schedule

d) Request additional resources