During a project review, it is found that a task is costing more than expected. What should

Question:

During a project review, it is found that a task is costing more than expected. What should the project manager do first?

a) Update the project charter

b) Implement cost compression techniques

c) Evaluate the impact of the cost overrun on the project budget

d) Request additional funds