During a project review, it is found that a task is costing more than expected. What should
Question:
During a project review, it is found that a task is costing more than expected. What should the project manager do first?
a) Update the project charter
b) Implement cost compression techniques
c) Evaluate the impact of the cost overrun on the project budget
d) Request additional funds
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
PMP Exam Prep 2025 1000 Practice Questions And Answers With Explanation For The PMP Exam
ISBN: 9798227759948
1st Edition
Authors: Claire Georgette Wiman
Question Posted: