During project execution, a deliverable is found to be incomplete. What should the project manager do? a)
Question:
During project execution, a deliverable is found to be incomplete.
What should the project manager do?
a) Ignore the issue and continue with the project
b) Document the issue and initiate corrective action to complete the deliverable
c) Reject the deliverable and inform the team
d) Update the project scope statement