During the project execution phase, a key stakeholder requests a change to the project scope that will

Question:


During the project execution phase, a key stakeholder requests a change to the project scope that will add additional features to the final product. What should the project manager do first?

A. Accept the change request and immediately implement it B. Analyze the impact of the change on the project’s schedule and budget C. Inform the stakeholder that changes are not allowed during the execution phase D. Request approval from the project sponsor before taking any action