Exercise Figure 5.1 is a project WBS with cost apportioned by percentages. If the total project cost

Question:

Exercise Figure 5.1 is a project WBS with cost apportioned by percentages. If the total project cost is estimated to be $800,000, what are the estimated costs for the following deliverables?

a. Design
b. Programming
c. In-house testing

What weaknesses are inherent in this estimating approach?