How are organizational process assets updated during project closure? a) By defining new project objectives b) By
Question:
How are organizational process assets updated during project closure?
a) By defining new project objectives
b) By capturing and documenting lessons learned and best practices
c) By developing the project schedule
d) By identifying project risks
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
PMP Exam Prep 2025 1000 Practice Questions And Answers With Explanation For The PMP Exam
ISBN: 9798227759948
1st Edition
Authors: Claire Georgette Wiman
Question Posted: