How are organizational process assets updated during project closure? a) By defining new project objectives b) By

Question:

How are organizational process assets updated during project closure?

a) By defining new project objectives

b) By capturing and documenting lessons learned and best practices

c) By developing the project schedule

d) By identifying project risks