How can cost variance be managed? a) By having a strict project schedule b) By using a

Question:

How can cost variance be managed?

a) By having a strict project schedule

b) By using a robust change control process to evaluate and approve cost changes

c) By reducing stakeholder communication

d) By increasing the project scope