Stakeholders request additional features for the project deliverable. How should the project manager handle this request? a)
Question:
Stakeholders request additional features for the project deliverable. How should the project manager handle this request?
a) Approve the additional features without assessment
b) Assess the impact of the additional features on project scope, schedule, and budget, and then seek approval through the change control process
c) Reject the request to prevent scope creep
d) Implement the features and inform stakeholders later