What is cost variance? a) The amount of time that an activity or project is ahead or

Question:

What is cost variance?

a) The amount of time that an activity or project is ahead or behind the planned schedule

b) The difference between the planned cost and the actual cost

c) The total cost of the project

d) The approved version of the project budget