What is cost variance? a) The amount of time that an activity or project is ahead or
Question:
What is cost variance?
a) The amount of time that an activity or project is ahead or behind the planned schedule
b) The difference between the planned cost and the actual cost
c) The total cost of the project
d) The approved version of the project budget
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
PMP Exam Prep 2025 1000 Practice Questions And Answers With Explanation For The PMP Exam
ISBN: 9798227759948
1st Edition
Authors: Claire Georgette Wiman
Question Posted: