What is included in the activity attributes? a) Detailed project budget b) Information about the activity, such
Question:
What is included in the activity attributes?
a) Detailed project budget
b) Information about the activity, such as predecessors, successors, logical relationships, leads, and lags
c) Stakeholder register
d) Risk register