What is the best approach for handling schedule changes during a project? a) Reject all schedule changes

Question:

What is the best approach for handling schedule changes during a project?

a) Reject all schedule changes to avoid delays

b) Evaluate the impact of the changes and process them through the change control system

c) Implement the changes immediately to keep stakeholders happy

d) Ignore the changes and continue with the project