What is the main goal of the Manage Stakeholder Engagement process? a) To identify project stakeholders b)

Question:

What is the main goal of the Manage Stakeholder Engagement process?

a) To identify project stakeholders

b) To develop the project schedule

c) To communicate and work with stakeholders to meet their needs and expectations

d) To allocate project resources