What is the relationship between the project budget and the cost baseline? a) The cost baseline is

Question:

What is the relationship between the project budget and the cost baseline?

a) The cost baseline is the approved version of the project budget

b) The project budget is created after the cost baseline

c) The project budget and the cost baseline are the same

d) There is no relationship between them