What is the relationship between the project schedule and the schedule baseline? a) The schedule baseline is

Question:

What is the relationship between the project schedule and the schedule baseline?

a) The schedule baseline is the approved version of the project schedule

b) The project schedule is created after the schedule baseline

c) The project schedule and the schedule baseline are the same

d) There is no relationship between them