What should a project manager do if a change request is rejected by the change control board
Question:
What should a project manager do if a change request is rejected by the change control board (CCB)?
a) Implement the change anyway
b) Inform stakeholders of the rejection and document the decision
c) Escalate the rejection to the project sponsor
d) Ignore the CCB's decision
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
PMP Exam Prep 2025 1000 Practice Questions And Answers With Explanation For The PMP Exam
ISBN: 9798227759948
1st Edition
Authors: Claire Georgette Wiman
Question Posted: