What should a project manager do if they identify a procurement risk that cannot be mitigated? a)

Question:

What should a project manager do if they identify a procurement risk that cannot be mitigated?

a) Add more resources to the project immediately

b) Submit a change request and implement corrective actions

c) Consider accepting the risk or transferring it to the seller

d) Update the project charter

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: