Which of the following is the correct sequence of project management processes leading to the development of
Question:
Which of the following is the correct sequence of project management processes leading to the development of a project schedule?
A. Define activities, estimate activity durations, sequence activities, develop schedule B. Sequence activities, define activities, estimate activity durations, develop schedule C. Define activities, sequence activities, estimate activity durations, develop schedule D. Estimate activity durations, define activities, sequence activities, develop schedule