Why is it important to involve stakeholders in the Define Scope process? a) To ensure that the
Question:
Why is it important to involve stakeholders in the Define Scope process?
a) To ensure that the project is completed on time
b) To ensure that all stakeholder needs and requirements are captured and documented
c) To reduce project costs
d) To increase project scope
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
PMP Exam Prep 2025 1000 Practice Questions And Answers With Explanation For The PMP Exam
ISBN: 9798227759948
1st Edition
Authors: Claire Georgette Wiman
Question Posted: