A work breakdown structure, project schedule, and cost estimates are outputs of the ______ process. a. initiating
Question:
A work breakdown structure, project schedule, and cost estimates are outputs of the ______ process.
a. initiating
b. planning
c. executing
d. monitoring and controlling
e. closing
LO.1