Given all the estimating done to determine the LO6 duration of project activities, what does it mean

Question:

Given all the estimating done to determine the LO6 duration of project activities, what does it mean to say that “only after the fact do we know which path was actually the critical path?”

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management In Practice

ISBN: 9780470121641

3rd Edition

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Scott M. Shafer, Margaret M. Sutton

Question Posted: