If a project is halfway completed, its schedule performance index is 110 percent, and its cost performance

Question:

If a project is halfway completed, its schedule performance index is 110 percent, and its cost performance index is 95 percent, how is it progressing?

a. It is ahead of schedule and under budget.

b. It is ahead of schedule and over budget.

c. It is behind schedule and under budget.

d. It is behind schedule and over budget.