Project Human Resource Management.

a. Assume that the Marketing person will be unavailable for one week, two months into the project, and for another week, four months into the project. Make adjustments to accommodate this unavailability so the schedule does not slip and costs do not change. Document the changes from the original plan and the new plan.

b. Add to each resource a 5% raise that starts three months into the project. Print a new budget report.

c. Use the Resource Usage view to see each person’s work each month. Print a copy.