Q3.32. When receiving change requests for a project, it is important that the impact analysis includes this
Question:
Q3.32. When receiving change requests for a project, it is important that the impact analysis includes this often forgotten piece of information.
(a) Resource required for performing the change
(b) Cost of change
(c) Requestor’s name
(d) Impact of not doing the change
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Determining Project Requirements Mastering The BABOK And The CBAP Exam
ISBN: 9781439896518,978-0367380861
2nd Edition
Authors: Hans Jonasson