Q3.32. When receiving change requests for a project, it is important that the impact analysis includes this

Question:

Q3.32. When receiving change requests for a project, it is important that the impact analysis includes this often forgotten piece of information.

(a) Resource required for performing the change

(b) Cost of change

(c) Requestor’s name

(d) Impact of not doing the change