Q3.35. For a large project, business analysis activities may be planned using the rolling wave approach. This means that:
(a) You only estimate the things that will be done in the next 30 days.
(b) You plan in 30-day increments and then do a gate review.
(c) You plan near-term work in detail and things further out at a high level.
(d) You plan near-term work in detail.