Q3.8. You are performing a stakeholder analysis and want to assess how involved the different stakeholders will

Question:

Q3.8. You are performing a stakeholder analysis and want to assess how involved the different stakeholders will be with the project solution. Which technique would help you document this?

(a) The RACI chart

(b) The onion diagram

(c) The context diagram

(d) The communications plan