Refer back to Problem 20. Assume the $590,000 indicated for Week 22 is the most likely BCWP.
Question:
Refer back to Problem 20.
Assume the $590,000 indicated for Week 22 is the most likely BCWP. Given a BCAC of $990,000, this represents 59.6 percent of the project completed. Suppose an expert assesses the LOGON project at that time using various measures and concludes that LOGON is between 50 percent and 65 percent completed. Let these represent pessimistic and optimistic scenarios.
Compute the corresponding pessimistic, most likely and optimistic scenarios.
Compute the corresponding pessimistic, most likely, and optimistic CPIs, SPIs, EACs, and forecast completion dates for the project.