Sally is the project manager for the NAA Project in her organization. She is about to create

Question:

Sally is the project manager for the NAA Project in her organization. She is about to create the WBS based on the approved project scope for her project. She would like to include several key stakeholders in the creation of the WBS. What is the primary benefit of including the stakeholders in the WBS creation process?

A. Including stakeholders ensures that all of the requirements are identified and captured.

B. Including stakeholders ensures that the stakeholders know who the project manager is and who the project team members are.

C. Including stakeholders ensures that the stakeholders see that all of the requirements have been identified and are accounted for in the project.

D. Including stakeholders helps to promote shared ownership of the project.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

It Project Management

ISBN: 9780071700436

3rd Edition

Authors: Joseph Phillips

Question Posted: