Screening Model. Assume that the following criteria relevant to the process of screening various construction project opportunities

Question:

Screening Model. Assume that the following criteria relevant to the process of screening various construction project opportunities are weighted in importance as follows:

• Safety (10)

• Speed to completion (5)

• Sustainable development (4)

• Infrastructure modifications (3)

• Traffic congestion (5)

• Cost (8)

Our company has four project alternatives that satisfy these key features as follows:

image text in transcribed

Construct a project screening matrix to identify among these four projects the most likely candidate to be implemented.