Screening Model. Assume that the following criteria relevant to the process of screening various construction project opportunities
Question:
Screening Model. Assume that the following criteria relevant to the process of screening various construction project opportunities are weighted in importance as follows:
• Safety (10)
• Speed to completion (5)
• Sustainable development (4)
• Infrastructure modifications (3)
• Traffic congestion (5)
• Cost (8)
Our company has four project alternatives that satisfy these key features as follows:
Construct a project screening matrix to identify among these four projects the most likely candidate to be implemented.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 9780134730714
5th Edition
Authors: Jeffrey K. Pinto
Question Posted: