The execution phase of the IT project has just finished. The goals of this project were to
Question:
The execution phase of the IT project has just finished. The goals of this project were to update order-entry systems for your company’s shipping department. Which of the following is the next step in the process of completing the project?
a. Gaining acceptance or the project by your shipping department
b. Finishing the work
c. Closing the contract
d. Releasing the resources