The following project network and associated costs are given (T in days, C in $1,000s) a. Verify

Question:

The following project network and associated costs are given (T in days, C in

$1,000s)image text in transcribed

a. Verify that the normal completion time is 22 days and that the direct cost is $3,050.

b. What is the least costly way to reduce the project completion time to 21 days? What is the project cost?

c. What is the least costly way to reduce the completion time to 20 days? What is the project cost?

d. Now, what is the earliest the project can be completed and what is the least costly way of doing this? What is the project cost?image text in transcribed

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: