Using the information from the following table, create an AON network activity diagram: a. Calculate each activity

Question:

Using the information from the following table, create an AON network activity diagram:

a. Calculate each activity TE (rounding to the nearest integer), the total duration of the project, its early start, early finish, late start, and late finish times, and the slack for each activity. Finally, show the project’s critical path.

b. Now, assume that activity E has taken 10 days past its anticipated duration to complete. What happens to the project’s schedule? Has the duration changed? Is there a new critical path? Show your conclusions.

image text in transcribed

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: