When a project is taking more hours to complete than originally planned, which of the following is
Question:
When a project is taking more hours to complete than originally planned, which of the following is a viable solution to reduce the hours required while maintaining costs?
A. Use less expensive materials.
B. Fast-track the project.
C. Assign additional resources.
D. Apply management reserve.